Questions and Answers: Size and Cost Estimation of Software
Last updated: October 08, 2022 Read in fullscreen view



- 01 Aug 2024
The Standish Group report 83.9% of IT projects partially or completely fail 1334
- 02 Nov 2021
What is Terms of Reference (ToR)? 1283
- 03 Apr 2022
Microsoft Solutions Framework (MSF) 1032
- 18 Oct 2021
Key Elements to Ramping Up a Large Team 989
- 13 Apr 2024
Lessons on Teamwork and Leadership from Chinese story book "Journey to the West" 736
- 20 Jul 2022
Software Myths and Realities 665
- 19 Oct 2021
Software development life cycles 614
- 02 May 2022
What Is RAID in Project Management? (With Pros and Cons) 613
- 14 Jun 2022
Example and Excel template of a RACI chart in Software Development 581
- 18 Dec 2023
The Cone of Uncertainty in Scrum & Requirement Definition 556
- 13 Jan 2020
Quiz: Test your understanding project cost management 533
- 28 Jul 2022
POC, Prototypes, Pilots and MVP: What's the differences? 523
- 18 Jul 2021
How To Ramp Up An Offshore Software Development Team Quickly 454
- 12 Oct 2022
14 Common Reasons Software Projects Fail (And How To Avoid Them) 444
- 27 Jan 2020
Should a project manager push developers to work more hours due to mistakes of manager schedule setting? 401
- 13 Oct 2021
Outsourcing Software Development: MVP, Proof of Concept (POC) and Prototyping. Which is better? 384
- 28 Oct 2022
Build Operate Transfer (B.O.T) Model in Software Outsourcing 340
- 07 Jul 2022
Managing Project Execution Terms 336
- 12 Dec 2021
Zero Sum Games Agile vs. Waterfall Project Management Methods 335
- 03 Jan 2023
Organizing your agile teams? Think about M.A.T (Mastery, Autonomy, Purpose) 330
- 12 Aug 2022
What is End-to-end project management? 329
- 17 Oct 2021
Does Fast Tracking increase project cost? 308
- 05 Mar 2021
How do you minimize risks when you outsource software development? 305
- 26 Sep 2024
Successful Project Management Techniques You Need to Look Out For 304
- 10 Apr 2024
The Parking Lot Method: Unlocking a Simple Secret to Supercharge Your Productivity 303
- 04 Oct 2021
Product Validation: The Key to Developing the Best Product Possible 280
- 09 May 2022
Build one to throw away vs Second-system effect: What are differences? 280
- 06 Jun 2022
Change Management at the Project Level 275
- 04 Oct 2022
Which ERP implementation strategy is right for your business? 242
- 01 Aug 2022
Is planning "set it and forget it" or "set it and check it"? 236
- 22 May 2022
What are common mistakes that new or inexperienced managers make? 236
- 15 May 2022
20 Common Mistakes Made by New or Inexperienced Project Managers 230
- 02 Nov 2022
Difference between Change Management and Project Management 196
- 01 Dec 2023
Laws of Project Management 195
- 31 Aug 2022
What are the best practices for software contract negotiations? 194
- 02 Dec 2021
3 Ways to Avoid Scope Creep in IT Consulting 185
- 02 Jun 2024
Reviving Ancient Wisdom: The Spiritual Side of Project Management 184
- 24 Nov 2023
The project management paradox: Achieving MORE by doing LESS 174
- 10 May 2022
Levels of Teamwork 166
- 01 May 2024
Warren Buffett’s Golden Rule for Digital Transformation: Avoiding Tech Overload 164
- 05 Sep 2023
The Cold Start Problem: How to Start and Scale Network Effects 140
- 07 Dec 2023
12 project management myths to avoid 139
- 30 Nov 2023
Project Managers, Focus on Outcomes — Not Deliverables 139
- 23 Jun 2024
Best Practices for Managing Project Escalations 124
- 21 Jun 2024
Dead Horses and the Escalation of Commitment 121
- 06 Mar 2024
[SemRush] What Are LSI Keywords & Why They Don‘t Matter 111
- 01 Mar 2024
10 Project Management Myths 107
- 05 Jun 2023
Fractional, Part-Time (virtual) or Interim CTO: Who Will Cover Your Business Needs? 94
- 12 Aug 2024
Understanding Google Analytics in Mumbai: A Beginner's Guide 70
This set of Software Engineering Multiple Choice Questions & Answers (MCQs) focuses on “Size and Cost Estimation of Software”.
Questions
1. Which of the following are parameters involved in computing the total cost of a software development project?
a) Hardware and software costs
b) Effort costs
c) Travel and training costs
d) All of the mentioned
2. Which of the following costs is not part of the total effort cost?
a) Costs of networking and communications
b) Costs of providing heating and lighting office space
c) Costs of lunch time food
d) Costs of support staff
3. What is related to the overall functionality of the delivered software?
a) Function-related metrics
b) Product-related metrics
c) Size-related metrics
d) None of the mentioned
4. A _________ is developed using historical cost information that relates some software metric to the project cost.
a) Algorithmic cost modelling
b) Expert judgement
c) Estimation by analogy
d) Parkinson’s Law
5. It is often difficult to estimate size at an early stage in a project when only a specification is available
a) True
b) False
6. Which technique is applicable when other projects in the same analogy application domain have been completed?
a) Algorithmic cost modelling
b) Expert judgement
c) Estimation by analogy
d) Parkinson’s Law
7. Which model assumes that systems are created from reusable components, scripting or database programming?
a) An application-composition model
b) A post-architecture model
c) A reuse model
d) An early design model
8. Which of the following states that work expands to fill the time available.
a) CASE tools
b) Pricing to win
c) Parkinson’s Law
d) Expert judgement
9. Which model is used during early stages of the system design after the requirements have been established?
a) An application-composition model
b) A post-architecture model
c) A reuse model
d) An early design model
10. Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools?
a) An application-composition model
b) A post-architecture model
c) A reuse model
d) An early design model
11. The COCOMO model takes into account different approaches to software development, reuse, etc.
a) True
b) False
Answers
- Answer: D
Explanation: All these are accounted for in estimating a software development cost. - Answer: C
Explanation: This is a incurred by the employees. - Answer: A
Explanation: Productivity is expressed in terms of the amount of useful functionality produced in some given time. Function points and object points are the best-known metrics of this type. - Answer: A
Explanation: The model uses a basic regression formula with parameters that are derived from historical project data and current as well as future project characteristics. - Answer: A
Explanation: Function-point and object-point estimates are easier to produce than estimates of code size but are often still inaccurate. - Answer: C
Explanation: The cost of a new project is estimated by analogy with these completed projects. - Answer: A
Explanation: It is designed to make estimates of prototype development. - Answer: C
Explanation: The cost is determined by available resources rather than by objective assessment. If the software has to be delivered in 12 months and 5 people are available, the effort required is estimated to be 60 person-months. - Answer: D
Explanation: Estimates are based on function points, which are then converted to number of lines of source code. The formula follows the standard form discussed above with a simplified set of seven multipliers. - Answer: C
Explanation: None. - Answer: B
Explanation: Its the COCOMO-2 model. COCOMO 2 incorporates a range of sub-models that produce increasingly detailed software estimates.